Butler's Bridge Replacement Project Darlene McWhirter Jul 31, 2018

For Immediate Release

July 31, 2018

 

BRIDGE REPLACEMENT PROJECT ON NH 113 IN TAMWORTH
CURRENT BRIDGE CLOSING AUGUST 2ND FOR FOUR WEEKS

 

The New Hampshire Department of Transportation announces the upcoming replacement of the NH Route 113 bridge over Bearcamp River in Tamworth will require the closure of the bridge to traffic for four weeks, beginning on Thursday, August 2, 2018.

 

During the bridge removal and replacement operations, traffic will be detoured via NH Routes 25 and 16.

 

CPM Constructors, of Freeport, Maine is the general contractor for the $2.5 million project, which has a final completion date of November 30, 2018

 